Seasonal, High Season and Closure Policy
Document control
Document code: RJ-LS-10
Version: 3.2
Version date: 3 November 2026
Effective date: 1 December 2026 — applies to orders placed from that date
Issued by: Ralph Jacobs SA (Pty) Ltd (reg. 2019/101093/07) and Ralph Jacobs NZ Limited (company no. 9334729) — see Where We Sell for which company sells to you
Supersedes: version 3.1, for orders placed from 1 December 2026 (3.1 still governs orders placed before then)
Approved: director, 3 November 2026 (RJ-PUB-16, signed)
1. Purpose
This Policy explains how high season, supplier closure, production closure, courier congestion, public holidays and reduced-capacity periods affect orders, repairs, resizing, returns and deliveries.
If you are buying from outside South Africa, read this together with Where We Sell and Who You Buy From.
2. When a longer delivery period applies
Where high season or a closure period means your order will take longer than our standard delivery periods (Terms section 9: 30 working days with a laboratory-grown stone, 40 working days with a natural stone), we tell you the longer period before you place the order and ask you to accept it. If we have not told you, the standard period applies.
3. High season
High season may include October, November, December, Valentine’s Day, wedding season peaks, promotional campaigns, supplier deadlines and any other period where order volume or operational risk increases.
We publish the exact dates for each season on this page before they affect any order. Current dates are in section 8. Where no dates are shown, no seasonal extension applies.
4. Production closure
During closure or reduced-capacity periods, Ralph Jacobs may pause or limit:
- custom manufacturing;
- sourcing;
- repairs;
- resizing;
- engraving;
- warranty assessments;
- returns assessments;
- collection slots;
- courier dispatch; and
- customer service response speed.
5. Order queue
Queue position may depend on the latest of:
- cleared payment;
- final customer approval;
- final specification;
- required customer documents;
- required FIC/AML/CFT/fraud/payment/customs checks;
- stone/component availability; and
- written acceptance of seasonal timing where required.
6. Event dates
If your piece is for a proposal, a wedding, travel or another fixed date, tell us before you order. Please do not rely on an estimate for a date that matters. We will either give you a specific written commitment or tell you plainly that we cannot meet the date.
7. Returns and warranty during closure
We acknowledge returns, repairs, warranty claims and complaints during a closure, and schedule the physical assessment for when we reopen. A closure does not pause your statutory rights or extend any deadline the law gives you. Urgent and safety matters are dealt with during the closure.
8. Current season dates
Festive closure 2026–2027
| Last order date for our standard delivery periods | 30 November 2026, 23:59:59 (South African time). Orders placed by then, and paid in full by 23:59:59 on 1 December 2026, have the delivery periods in Terms section 9. |
| Manufacturing closed to new orders | 1 December 2026 to 10 January 2027. We finish and dispatch orders placed by 30 November 2026 during December. New work starts on 11 January 2027. |
| Orders placed from 1 December 2026 to 10 January 2027 | We make your piece when we reopen. Your delivery period counts from 11 January 2027, or from the first working day after we receive your payment if that is later: 30 working days with a laboratory-grown stone, moissanite, no stone or your own stone (by 19 February 2027 for an order paid before 11 January) and 40 working days with a natural stone (by 5 March 2027). Add up to 10 working days for delivery outside South Africa. We show you this period before you order and ask you to accept it. |
| Orders placed on or before 30 November 2026 | Your delivery period does not change, as long as it is paid in full by 23:59:59 on 1 December 2026. An order not paid by then is cancelled, and you can place it again on the terms shown at that time. We work through orders in the order payments clear (section 5) and aim to deliver before 25 December 2026 where we can, but we do not promise a Christmas date. If you need your piece by a set date, tell us before you order (section 6). |
| Offices | Closed on public holidays (16 December, 25 and 26 December, 1 January). Our team works remotely from 1 December 2026 to 10 January 2027. |
| Customer service | We aim to reply within 48 hours. |
| Suspended from 1 December 2026 to 10 January 2027 | Manufacturing of orders placed from 1 December 2026; resizing, repairs and engraving; physical returns and warranty assessments; and collections. You can still ask for a resize or repair during this period: a request made in time (for example within the 60 days of the Ring Resize Benefit) stays in time, and we do the work from 11 January 2027. |
| Delivery during the closure | Orders placed by 30 November 2026 are delivered by courier only; there are no collections. Delivery takes at least 3 working days after dispatch, not counting public holidays. If you chose collection when you ordered, you choose: we deliver by courier at no charge, or you collect from 11 January 2027. We contact you before your piece is ready. |
| Returns, repairs and warranty | We acknowledge every request within 48 hours and assess items from 11 January 2027. Refunds the law requires are paid on time. The closure does not pause your statutory rights or extend any deadline the law gives you (section 7). |
From 11 January 2027 the standard delivery periods in Terms section 9 apply again.
Every legal publication issued by Ralph Jacobs, grouped by category. Each entry shows its current version, status and effective date. Superseded and withdrawn versions are retained permanently and stay reachable at their original addresses, so a version you accepted or downloaded in the past can still be read and verified.